Electrical Panel and Service Upgrade in Ontario: The Complete 100A to 200A Guide
Your 100A panel was installed when the biggest electrical load in the house was a toaster. Today you need EV chargers, heat pumps, and home offices — and the math doesn’t work anymore. Here’s what a proper upgrade actually involves.
A Rule 8-200 load calculation decides whether you need 200 A. An EV charger alone can push a typical 100 A house over.
An energy management system can let new loads share a 100 A service (OESC Rule 8-106 11)).
The work takes about a day; the utility and ESA steps take weeks.
The Short Answer
- A panel upgrade replaces the breaker panel. A service upgrade (100 A to 200 A) also replaces the meter base and the service conductors, and often the mast. Your utility is involved in both.
- A Licensed Electrical Contractor files an ESA notification. The utility disconnects, the work is done, ESA inspects, and the utility reconnects. The house is usually without power for 1–2 days.
- Ontario contractors’ published 2026 price guides put a 100 A to 200 A upgrade at roughly $2,500–$5,000 (details in the cost section).
- Lead time is set by the utility: from about two weeks to a couple of months.
- Check first whether you need it: a Rule 8-200 calculation, or an energy management system, may keep you on 100 A.
Why Upgrade from 100A to 200A?
Ontario homes built before 1980 typically have 100A service — sometimes even 60A. This was adequate for the era, but modern electrical demands have fundamentally changed:
| Load | Typical circuit | How the Rule 8-200 calculation counts it |
|---|---|---|
| Level 2 EV Charger | 30–50A (240V) | 100 % of its rating (item vi), unless an energy management system controls it (Rule 8-106 11)) |
| Electric Range/Oven | 40–50A | 6,000 W for a range up to 12 kW, plus 40 % of the rating above 12 kW (item iv) |
| Central A/C | 20–30A | 100 % (item iii); with interlocked electric heat, only the larger of the two (Rule 8-106 3)) |
| Heat Pump | 30–60A | Heating per Section 62, cooling at 100 % (item iii); see the heat pump sizing guide |
| Electric Dryer | 30A | 25 % of its rating when a range is provided for (item vii) |
| Hot Tub / Spa | 40–50A | Its water heater at 100 % (item v) |
Planning a heat pump? The heat pump sizing guide starts with the CSA F280 heat-loss calculation and ends with the circuit and the panel.
Adding up breaker sizes overstates the load. The code sizes a service from the calculated load, and it counts each appliance differently (right-hand column). The worked example below shows how one Ontario house comes out.
Panel Upgrade vs Service Upgrade
The two terms are often mixed up, and the difference decides the scope, the utility’s role and the price.
| Panel replacement (same amperage) | Service upgrade (e.g. 100 A → 200 A) | |
|---|---|---|
| Typical reason | Old, damaged or flagged panel (fuses, Stab-Lok); no spare spaces | More capacity: EV charger, heat pump, addition, extra unit |
| What changes | The panel and its breakers | Panel, meter base, service conductors; often the mast and weatherhead; grounding brought up to code |
| Utility | Isolation (disconnect and reconnect) | A service upgrade request to the utility, plus disconnect and reconnect |
| ESA | Notification and inspection | Notification and inspection |
| Indicative price (contractors’ 2026 guides) | About $1,800–$3,000+ | About $2,500–$5,000 |
The service entrance design guide covers the meter base, the metering and the service conductors in more depth.
8 Signs You Need a Panel Upgrade
- Breakers trip frequently — especially when multiple appliances run simultaneously
- Fuse panel or older breaker panel — screw-in fuse panels and some older breaker panels (e.g., Federal Pioneer Stab-Lok, Zinsco) are often flagged by inspectors and insurers
- Adding EV charging — Level 2 chargers typically require 30–50A dedicated circuits at 240V
- Renovation or addition — basement apartments, additions, or kitchen remodels
- Double-tapped breakers — two wires on a breaker terminal not rated for two conductors = code violation
- Insurance requirement — many insurers won’t cover homes with 60A/100A fuse panels
- Real estate transaction — home inspection flagged the panel
- No spare breaker spaces — tandem breakers or a full panel leave no room for an EV charger or heat pump circuit
Do You Need 200 A? A Worked Load Calculation
For a single house, Rule 8-200 sets the calculated load as the greater of two values: (a) a calculation of the house and its appliances, and (b) a fixed minimum. Here is how it works, step by step.
Step 1: Living area (Rule 8-110)
Living area is measured from the inside dimensions:
- 100 % of the ground floor;
- 100 % of the areas above it used for living;
- 75 % of the areas below the ground floor that are more than 1.8 m high.
Step 2: The two values (Rule 8-200 1))
Value (a) adds up these items:
- i) 5,000 W for the first 90 m² of living area;
- ii) 1,000 W for each further 90 m² or portion;
- iii) electric space heating (Section 62 demand factors) and air conditioning at 100 %, subject to Rule 8-106 3);
- iv) the range: 6,000 W, plus 40 % of the rating above 12 kW;
- v) tankless water heaters and water heaters for steamers, pools, hot tubs or spas at 100 %;
- vi) EV charging equipment at 100 %, except as Rule 8-106 11) allows;
- vii) every other load over 1,500 W at 25 % when a range is provided for. Without a range: 100 % of the combined load up to 6,000 W plus 25 % of the rest.
Value (b) is 24,000 W where the floor area excluding the basement is 80 m² or more (100 A at 240 V), or 14,400 W (60 A) below 80 m².
Step 3: One house, four scenarios
Take a typical older Ontario bungalow: a 110 m² ground floor (inside dimensions), a 110 m² basement with more than 1.8 m headroom, a gas furnace and a gas water heater. The appliance ratings are assumed for illustration. Living area = 110 + 0.75 × 110 = 192.5 m².
| Item (Rule 8-200 1) a)) | A. Today | B. + EV charger | C. + EV charger with EMS | D. + EV charger + hot tub |
|---|---|---|---|---|
| i) Basic, first 90 m² | 5,000 W | 5,000 W | 5,000 W | 5,000 W |
| ii) 102.5 m² more = 2 portions of 90 m² | 2,000 W | 2,000 W | 2,000 W | 2,000 W |
| iii) Central A/C, 4.0 kW (assumed) | 4,000 W | 4,000 W | 4,000 W | 4,000 W |
| iv) Range, 12 kW | 6,000 W | 6,000 W | 6,000 W | 6,000 W |
| v) Hot tub heater, 5.5 kW (assumed) | — | — | — | 5,500 W |
| vi) EV charger, 32 A × 240 V = 7,680 W | — | 7,680 W | not counted (Rule 8-106 11)) | 7,680 W |
| vii) Dryer, 5.0 kW (assumed) × 25 % | 1,250 W | 1,250 W | 1,250 W | 1,250 W |
| (a) total | 18,250 W | 25,930 W | 18,250 W | 31,430 W |
| (b) minimum (≥ 80 m² above the basement) | 24,000 W | 24,000 W | 24,000 W | 24,000 W |
| Calculated load (greater) | 24,000 W = 100 A | 25,930 W ≈ 108 A | 24,000 W = 100 A | 31,430 W ≈ 131 A |
| Result | 100 A is enough | Over 100 A | 100 A is enough | Needs more than 100 A; most owners go to 200 A |
The Rule 8-200 calculation for one house, four scenarios
One illustrative Ontario house; appliance ratings are assumed for illustration.
Parts
A. Today: 18,250 W of items; the 24,000 W minimum governs, so 100 A is enough. Rule 8-200 1) b)
B. + EV charger: 7,680 W at 100 % takes the total to 25,930 W, about 108 A. Rule 8-200 1) a) vi)
C. + EV charger with EMS: the charger is left out where an energy management system controls the load; the minimum governs again. Rules 8-106 11), 8-500
D. + EV charger + hot tub: the hot tub heater at 100 % brings the total to 31,430 W, about 131 A; most owners go to 200 A. Rule 8-200 1) a) v)
- Basic load (i + ii)
- Central A/C (iii)
- Range (iv)
- Dryer at 25 % (vii)
- EV charger (vi)
- Hot tub heater (v)
- Not counted with an energy management system
- A. The minimum in (b) governs, so 100 A is compliant.
- B. One Level 2 charger takes the same house over 100 A. The EV-ready wiring guide shows the 40 A circuit for a 32 A charger.
- C. OESC Rule 8-106 11) (an Ontario amendment) lets the charger’s load be left out where an energy management system monitors the service and controls the load under Rule 8-500. Rule 8-500 also says the system must not push a circuit, feeder or service past Rule 8-104 5) or 6).
- D. With a hot tub as well, the house needs more than 100 A. 200 A is the usual next step and leaves room for a heat pump later (see the heat pump sizing guide).
Your electrician or engineer does this with your real nameplate ratings; the table shows the method, not your answer.
Alternatives to a service upgrade
- An energy management system (Rules 8-106 10) and 11), 8-500). The EV charging guide explains how one shares a service among chargers.
- The existing-load method, Rule 8-106 8). When loads are added to an existing service, the new load may be calculated by adding the new loads (with code demand factors) to the maximum demand measured over the most recent 12 months, still subject to Rule 8-104 5) and 6).
- Moving loads to gas, or interlocking loads so only one runs at a time (Rule 8-106 2) and 3)).
Converting a house to two or three units, or planning a service above 200 A? ETEM prepares the load calculation, single-line diagram and utility submission. Discuss your project.
CEC & OESC Requirements
A panel upgrade isn’t just swapping a box. The Canadian Electrical Code (CEC) and Ontario Electrical Safety Code (OESC) mandate specific requirements:
| Requirement | Reference | Details |
|---|---|---|
| Minimum service size | CEC Rule 8-200 | The calculated load is the greater of the Rule 8-200 1) a) calculation and 24,000 W (100 A at 240 V) where the floor area excluding the basement is 80 m² or more, or 14,400 W (60 A) below 80 m²; the former OBC 200A EV-ready provision (O. Reg. 139/17) was revoked in 2019 |
| Demand calculation | CEC Rule 8-200 | Single-dwelling calculation: 5000W basic load for the first 90 m² of living area (per Rule 8-110) + 1000W per additional 90 m² or portion thereof, plus heating/A/C, range, EVSE and 25% of other loads over 1500W where a range is provided for; see the worked example |
| Living area | CEC Rule 8-110 | Inside dimensions: 100 % of the ground floor, 100 % of the areas above it used for living, and 75 % of the areas below the ground floor that are more than 1.8 m high |
| Service conductor | CEC Rule 4-006 | 3/0 AWG copper (75°C column, per termination rating) for 200A |
| Grounding electrode | CEC Rule 10-102 | Grounding electrode system required; may include ground rods, a metallic water pipe (in-situ electrode), or a concrete-encased electrode; see the grounding and bonding guide |
| AFCI protection | CEC Rule 26-658 | Required on dwelling-unit receptacle branch circuits (with listed exceptions); per ESA Bulletin 26-29-6, not retroactively required on existing circuits during panel swap if no new receptacles added; see the AFCI requirements guide |
| Spare spaces | CEC Rule 8-108 1) | A new panelboard in a single dwelling must have at least four additional spaces for future overcurrent devices, with provision for a two-pole device |
| Panel clearance | CEC Rule 2-308 | A minimum working space of 1 m with secure footing in front of the panelboard, with room for its door to open at least 90° |
For a detailed breakdown of demand calculations, see our Load Calculations & Transformer Sizing guide.
Why 3/0 copper for 200 A? The wire size and ampacity guide explains the 75 °C column of CEC Table 2 and Rule 4-006.
A 100 A to 200 A service upgrade
A typical older house, not a specific project. Equipment is drawn larger than scale.
Parts
Service mast and weatherhead: replaced if the old mast is undersized for 200 A conductors. The utility disconnects first and reconnects only after ESA approval.
Meter base: a 100 A meter base is replaced with a 200 A rated base.
Service conductors: 3/0 AWG copper for 200 A, from the 75 °C column to match the termination rating. Rule 4-006
New 200 A panel with main breaker. Service size comes from the calculated load: the greater of the Rule 8-200 1) a) calculation and 24,000 W (100 A at 240 V) where the floor area excluding the basement is 80 m² or more, or 14,400 W (60 A) below 80 m². Rule 8-200
Working space. A minimum working space of 1 m with secure footing in front of the panelboard, with room for its door to open at least 90°. Rule 2-308
Grounding electrode: ground rods, a metallic water pipe (in-situ electrode) or a concrete-encased electrode. Rule 10-102
AFCI: required on new or extended receptacle branch circuits; not retroactively on existing circuits during a panel swap. Rule 26-658 · ESA Bulletin 26-29-6
The work needs an ESA notification, and the ESA inspection comes before the utility reconnects.
- Service conductors in conduit
- Grounding and bonding conductor
- Working space in front of the panel
- Door opening at least 90°
The Upgrade Process Step-by-Step
| Step | Who | Timeline |
|---|---|---|
| 1. Load assessment | LEC; P.Eng where required | Day 1 |
| 2. ESA permit application | Licensed Electrical Contractor (LEC) | Day 1–3 |
| 3. LDC notification | LEC coordinates with utility | Varies by utility: see Requesting the Upgrade from Your Utility |
| 4. Utility disconnect | LDC (Toronto Hydro, Hydro One, Alectra) | Scheduled day |
| 5. Service mast & weatherhead | LEC | Same day |
| 6. New panel installation | LEC | Same day |
| 7. Grounding electrode | LEC | Same day |
| 8. ESA inspection | ESA Inspector | Before reconnection (book in advance) |
| 9. Utility reconnect | LDC | After ESA approval |
Important: The home is without power from Step 4 until Step 9 — typically 1–2 days. Plan accordingly. For utility coordination details, see our Toronto Hydro Connection Guide.
Requesting the Upgrade from Your Utility
The utility (local distribution company, LDC) owns the supply up to the service point, and its Conditions of Service set what it needs from you and your contractor. Each one has its own request process:
| Utility | Where | How to request | What it publishes |
|---|---|---|---|
| Toronto Hydro | Toronto | Online Service Upgrade Request Form | Contact within 10 business days. For simple overhead requests (120/240 V, up to 200 A), appointment availability is shown online in real time. Other requests go through a quotation, which typically takes up to 60 days after all information is received. |
| Alectra Utilities | Aurora, Brampton, Guelph, Hamilton, Markham, Mississauga, Richmond Hill, Vaughan | New Connections Portal → “Service Upgrade (>100A)”; the account must be in good standing | Simple upgrades (fuses to breakers, under 200 A) are typically reviewed and booked in 5–10 business days. About four weeks is typical for service designs for upgrades to 200 A or larger. Reconnection only after ESA connection authorization. Residential customers get one free planned disconnect every 12 months. |
| Hydro One | Rural Ontario and many smaller communities | Service upgrade request; contact ESA for a permit first | Contact within 15 days; timelines vary by location and queue. |
| Hydro Ottawa | Ottawa | Online Service Request form (“an electrical service upgrade”) | Submit 3–4 weeks before the project; contact within 10 business days. |
| London Hydro | London | Application by email through its Contractor Information page | Isolations fed from a pull-box may need extra time to schedule. |
| Other utilities | Elexicon Energy (Ajax, Pickering, Whitby), Oshawa Power, Burlington Hydro, Oakville Hydro, Milton Hydro, Newmarket-Tay Power, Enova Power (Kitchener, Waterloo), GrandBridge Energy (Brantford, Cambridge) | — | See the local notes on our city pages. |
Lead times change; check your utility’s page before you book the electrician.
ESA Permits & Inspections
In Ontario, most electrical work, including every panel or service upgrade, requires an ESA notification (permit). This is not optional — it is provincial law under the Electricity Act.
- If hiring someone, they must be a Licensed Electrical Contractor (LEC)
- ESA inspection is mandatory before the utility will reconnect
- A Certificate of Acceptance is issued upon passing inspection
- ESA allows homeowners to do electrical work only in their own home or rental building, and the work must meet the Ontario Electrical Safety Code, including the notification. Panel upgrades involve live service conductors — we strongly recommend hiring an LEC
For more on the permit process, see our Ontario Electrical Permit Guide.
What Does a Panel Upgrade Cost in Ontario?
Ontario electrical contractors that publish 2026 price guides put a 100 A to 200 A service upgrade at roughly $2,500 to $5,000, and a same-amperage panel replacement at roughly $1,800 to $3,000 or more (sources below). These are contractors’ published ranges, not ETEM quotes. A mast replacement, an underground service, a meter-base change, grounding work and utility charges can move a job outside them.
What drives the price
| Factor | Impact |
|---|---|
| Service mast replacement | Required if existing mast is undersized for 200A conductors |
| Meter base upgrade | 100A meter base must be replaced with 200A rated base |
| Underground vs. overhead | Underground service upgrades cost significantly more (trenching) |
| Grounding system | Older homes may need new ground rods and water pipe bonds |
| Number of circuits | More circuits to transfer = more labor |
| AFCI breaker requirements | AFCI may be required on new or extended receptacle branch circuits per the OESC (29th edition, in force May 1, 2025; CEC 2024); not retroactively required on existing circuits during a panel swap (ESA Bulletin 26-29-6) |
| Asbestos or vermiculite | Older homes may require hazmat assessment before work begins |
| LDC requirements | Some utilities charge reconnection or infrastructure fees |
How to compare quotes
Make sure each quote states:
- The ESA notification
- The meter base
- The mast and weatherhead
- Grounding electrode work
- AFCI on new or extended circuits
- Utility coordination and any utility charges
- The number of spaces in the new panel
- Drywall patching
- A written load calculation
Get accurate pricing: The only way to know the true cost is a site assessment by a Licensed Electrical Contractor. Request a free consultation from ETEM Engineering.
Choosing the New Panel: Spaces for Future Loads
Rule 8-108 1) requires at least four spare spaces, with provision for a two-pole device, at the time of installation. That is a minimum, not a plan. Count the two-pole circuits you may add, such as an EV charger, a heat pump, an induction range, a hot tub, a battery or solar, and choose the panel size with them in mind. The load calculation tells you whether the service can carry them.
Adding a Second or Third Unit
Since Bill 23 (More Homes Built Faster Act, 2022, in force 28 Nov 2022), most serviced residential lots in Ontario may have up to three units as of right: up to three in the main building, or two plus one in an ancillary building such as a garden suite.
The electrical consequences:
- The service calculation then covers more than one dwelling unit.
- Rule 8-202 3) sets the demand factors for a service supplying two or more dwelling units.
- Metering (one meter or one per unit) follows the utility’s Conditions of Service.
The P.Eng stamp guide explains when engineered drawings are needed, and the garden suite fire alarm guide covers the fire alarm requirements for a garden suite. Planning two or three units, or a service above 200 A? Talk to ETEM.
When Do You Need a P.Eng?
Not every panel upgrade requires a Professional Engineer. Here’s when you do:
| Scenario | P.Eng Typically Required? | Why |
|---|---|---|
| Simple 100A → 200A residential swap | No | LEC can typically complete load calculation, ESA notification, and installation |
| Service upgrade above 200A | Often / LDC-dependent | Larger services may require LDC load summary, drawings, or sealed letter; OESC plan review applies at ≥600A 1Φ or ≥400A 3Φ |
| Adding secondary suite / ADU | Depends | Building permit and municipality requirements vary; designer/BCIN or P.Eng may be required |
| Commercial panel upgrade | Likely yes / Depends | Minor work may only need LEC + ESA notification; larger services, permit drawings, or plan review may require P.Eng |
| Multi-unit residential | Often | Metering, demand calculations, service distribution, and permit submissions are commonly engineered |
For more details, read our P.Eng Stamp Requirements in Ontario article.
Frequently Asked Questions
How long does a panel upgrade take?
The installation usually takes a day; the house is without power from disconnect to reconnect, typically 1–2 days. The lead time is the utility’s. Toronto Hydro contacts you within 10 business days and cites a typical isolation lead time of about one month. Alectra books simple upgrades in 5–10 business days and allows about four weeks for 200 A service designs. Hydro Ottawa asks for requests three to four weeks ahead. Plan for several weeks from application to energization.
Can I upgrade from 100A to 400A?
Technically yes, but residential services above 200A are less common and require a detailed load calculation, LDC approval and, in Toronto, an underground supply (Toronto Hydro’s residential maximum is 400A). The utility may need to install a larger transformer.
Do I need a panel upgrade to install an EV charger?
Not always. A Rule 8-200 load calculation shows whether the service has room (see the worked example above). If it doesn’t, an energy management system can let the charger share a 100 A service (OESC Rules 8-106 10) and 11), 8-500), or the designer can add the new load to the highest demand measured over the last 12 months (Rule 8-106 8)). See our EV Charging Guide.
Is a panel upgrade covered by home insurance?
No — a panel upgrade is a home improvement, not an insurance claim. However, upgrading from a fuse panel or Federal Pacific panel may reduce your insurance premium or resolve coverage denials.
What is a Federal Pacific panel and why is it a concern?
In Canada, Stab-Lok panels were sold under the Federal Pioneer name (the Canadian counterpart of US Federal Pacific Electric) and were widely installed in Ontario homes. Independent testing, mainly of US Federal Pacific equipment, has raised concerns about breakers failing to trip under overload conditions. There has been no general recall of the panels (only limited recalls of specific breaker models), but many insurers and inspectors recommend an assessment or replacement.
Do I need a permit to upgrade an electrical panel in Ontario?
Yes. Every panel or service upgrade needs an ESA notification of work before it starts, and the utility reconnects only after the ESA inspection. Hydro One, for example, asks customers to contact ESA for a permit before any change to their electrical service.
Can a homeowner replace an electrical panel in Ontario?
ESA allows homeowners to do electrical work only in their own home or rental building, to the OESC and with a notification. Anyone you hire must be a Licensed Electrical Contractor. Because the work involves the utility supply, most homeowners hire an LEC.
How much does it cost to upgrade to 200 amp service in Ontario?
Contractors’ published 2026 guides put it at roughly $2,500–$5,000. A mast replacement, an underground service, a meter-base change, grounding work and utility charges push it higher. Get itemized quotes and compare them line by line (see the cost section).
What size wire do I need for a 200 amp service in Ontario?
3/0 AWG copper, from the 75 °C column of Table 2, to match the 75 °C termination rating (Rule 4-006). Aluminum conductors are sized from Table 4. See the wire size and ampacity guide.
Sources
- Ontario Electrical Safety Code, 29th edition (2024)Rules 2-308, 4-006, 8-104, 8-106 2), 3), 8)–11), 8-108, 8-110, 8-200, 8-202, 8-500, 10-102, 26-658; Table 2.
- ESA Bulletin 26-29-6 — Electrical replacement and/or alterations in dwelling units
- ESA — Can a homeowner file a notification of work?
- Toronto Hydro — Service upgrade request
- Alectra Utilities — Make a service request
- Hydro One — Service upgrade
- Hydro Ottawa — Service request
- London Hydro — Contractor information
- Environmental Registry of Ontario, notice 019-6197 — Additional Residential Units
- Lumos Electric (Ottawa) — Electrical panel upgradesJune 2026: $2,500–$5,000 (100 A to 200 A); $1,800–$3,000+ (same amperage).
- Superior Power Electric (Brampton) — Electrical panel upgrade cost Ontario 2026April 2026: $2,800–$5,000 (100 A to 200 A); $1,800–$3,000 (same amperage).
- Ottawa Electric Service — Electrical panel upgrade cost Ontario: 2026 pricesMarch 2026: $2,500–$4,500 (100 A to 200 A).
- O. Reg. 139/17 and the Electricity Act, 1998