Load Calculations & Transformer Sizing: A Practical Guide
An oversized transformer wastes capital and increases standby losses. An undersized one overheats, trips, and halts operations. Here's how to calculate electrical loads and size transformers correctly — with worked examples.
The Fundamentals
Connected Load vs. Demand Load
The connected load is the sum of all nameplate ratings of every piece of electrical equipment in a building. But not all equipment runs at the same time or at full capacity. The demand load accounts for this reality using demand factors.
Connected Load × Demand Factor = Demand Load
This is the actual load the electrical system must be designed to carry.
Demand Factor
The demand factor is the ratio of the maximum demand to the total connected load. It's always ≤ 1.0. For example, a building with 100kVA connected lighting but only 80kVA running simultaneously has a demand factor of 0.80.
The CEC provides specific demand factors for different load types:
| Load Type | CEC Rule | Typical Demand Factor |
|---|---|---|
| General lighting (first 10kVA) | Rule 8-200 | 100% |
| General lighting (over 10kVA) | Rule 8-200 | 70–90% |
| Receptacle loads (first 10kVA) | Rule 8-200 | 100% |
| Receptacle loads (over 10kVA) | Rule 8-200 | 70% |
| Electric heating | Rule 62 | 75–100% |
| Motors (largest) | Rule 8-104 | 125% |
| Motors (all others) | Rule 8-104 | 100% |
| Kitchen equipment | Rule 8-200 | 65–80% |
Diversity Factor
The diversity factor accounts for the probability that not all circuits will be at peak simultaneously. It applies when combining multiple feeders or sub-panels:
Diversity Factor = Sum of individual maximum demands ÷ Maximum demand of the whole system
Diversity factor is always ≥ 1.0 (the inverse of how demand factor works)
Worked Example: Small Commercial Building
Let's size the transformer for a 5,000 sq ft office building:
Step 1: Calculate Connected Loads
| Load | Calculation | VA |
|---|---|---|
| General lighting | 5,000 sqft × 15 VA/sqft | 75,000 |
| Receptacles | 5,000 sqft × 10 VA/sqft | 50,000 |
| HVAC (RTU #1) | 25 kVA nameplate | 25,000 |
| HVAC (RTU #2) | 15 kVA nameplate | 15,000 |
| Water heater | 5 kW | 5,000 |
| Total connected | 170,000 |
Step 2: Apply Demand Factors
| Load | Connected | Demand Factor | Demand VA |
|---|---|---|---|
| Lighting (first 10kVA) | 10,000 | 100% | 10,000 |
| Lighting (remaining) | 65,000 | 75% | 48,750 |
| Receptacles (first 10kVA) | 10,000 | 100% | 10,000 |
| Receptacles (remaining) | 40,000 | 70% | 28,000 |
| HVAC (largest motor × 125%) | 25,000 | 125% | 31,250 |
| HVAC (other motors) | 15,000 | 100% | 15,000 |
| Water heater | 5,000 | 100% | 5,000 |
| Total demand | 148,000 |
Step 3: Size the Transformer
Total demand = 148 kVA. Standard transformer sizes are: 75, 112.5, 150, 225, 300, 500, 750, 1000 kVA.
Select the next standard size up: 150 kVA transformer.
Engineering Judgment: Some engineers apply an additional 20–25% future capacity allowance. In this case, 148 × 1.25 = 185 kVA, which would push the selection to a 225 kVA transformer. This is a cost-benefit decision the client should be involved in.
The kVA Formula
The fundamental relationships you need:
Single Phase:
kVA = (V × I) / 1,000
Three Phase:
kVA = (V × I × √3) / 1,000
Current from kVA (Three Phase):
I = kVA × 1,000 / (V × √3)
Quick Reference: Transformer Full Load Amps
| Transformer kVA | FLA @ 208V | FLA @ 480V | FLA @ 600V |
|---|---|---|---|
| 75 | 208A | 90A | 72A |
| 112.5 | 312A | 135A | 108A |
| 150 | 416A | 180A | 144A |
| 225 | 625A | 271A | 217A |
| 300 | 833A | 361A | 289A |
| 500 | 1,388A | 601A | 481A |
| 750 | 2,082A | 902A | 722A |
| 1000 | 2,776A | 1,203A | 962A |
Common Sizing Mistakes
- Using connected load without demand factors — results in 30–50% oversizing
- Forgetting the 125% motor factor — CEC requires it for the largest motor
- Ignoring future capacity — adding EV charging, solar, or tenant loads later
- Mixing kW and kVA — kVA = kW ÷ power factor (PF typically 0.85–0.90)
- Not coordinating with the utility — transformer availability and lead times vary
Download the Load Calculation Worksheet
Get our Excel-based load calculation template — pre-formatted with CEC demand factors and standard formulas.
Need a Load Study or Capacity Assessment?
Our P.Eng team performs comprehensive electrical load studies, capacity assessments, and transformer sizing for buildings of any scale.
Get a Free Consultation