Load Calculations & Transformer Sizing: A Practical Guide

An oversized transformer wastes capital and increases standby losses. An undersized one overheats, trips, and halts operations. Here's how to calculate electrical loads and size transformers correctly — with worked examples.

Electrical Load Calculations and Transformer

The Fundamentals

Connected Load vs. Demand Load

The connected load is the sum of all nameplate ratings of every piece of electrical equipment in a building. But not all equipment runs at the same time or at full capacity. The demand load accounts for this reality using demand factors.

Connected Load × Demand Factor = Demand Load
This is the actual load the electrical system must be designed to carry.

Demand Factor

The demand factor is the ratio of the maximum demand to the total connected load. It's always ≤ 1.0. For example, a building with 100kVA connected lighting but only 80kVA running simultaneously has a demand factor of 0.80.

The CEC provides specific demand factors for different load types:

Load Type CEC Rule Typical Demand Factor
General lighting (first 10kVA)Rule 8-200100%
General lighting (over 10kVA)Rule 8-20070–90%
Receptacle loads (first 10kVA)Rule 8-200100%
Receptacle loads (over 10kVA)Rule 8-20070%
Electric heatingRule 6275–100%
Motors (largest)Rule 8-104125%
Motors (all others)Rule 8-104100%
Kitchen equipmentRule 8-20065–80%

Diversity Factor

The diversity factor accounts for the probability that not all circuits will be at peak simultaneously. It applies when combining multiple feeders or sub-panels:

Diversity Factor = Sum of individual maximum demands ÷ Maximum demand of the whole system
Diversity factor is always ≥ 1.0 (the inverse of how demand factor works)

Worked Example: Small Commercial Building

Let's size the transformer for a 5,000 sq ft office building:

Step 1: Calculate Connected Loads

Load Calculation VA
General lighting5,000 sqft × 15 VA/sqft75,000
Receptacles5,000 sqft × 10 VA/sqft50,000
HVAC (RTU #1)25 kVA nameplate25,000
HVAC (RTU #2)15 kVA nameplate15,000
Water heater5 kW5,000
Total connected170,000

Step 2: Apply Demand Factors

Load Connected Demand Factor Demand VA
Lighting (first 10kVA)10,000100%10,000
Lighting (remaining)65,00075%48,750
Receptacles (first 10kVA)10,000100%10,000
Receptacles (remaining)40,00070%28,000
HVAC (largest motor × 125%)25,000125%31,250
HVAC (other motors)15,000100%15,000
Water heater5,000100%5,000
Total demand148,000

Step 3: Size the Transformer

Total demand = 148 kVA. Standard transformer sizes are: 75, 112.5, 150, 225, 300, 500, 750, 1000 kVA.

Select the next standard size up: 150 kVA transformer.

Engineering Judgment: Some engineers apply an additional 20–25% future capacity allowance. In this case, 148 × 1.25 = 185 kVA, which would push the selection to a 225 kVA transformer. This is a cost-benefit decision the client should be involved in.

The kVA Formula

The fundamental relationships you need:

Single Phase:

kVA = (V × I) / 1,000

Three Phase:

kVA = (V × I × √3) / 1,000

Current from kVA (Three Phase):

I = kVA × 1,000 / (V × √3)

Quick Reference: Transformer Full Load Amps

Transformer kVA FLA @ 208V FLA @ 480V FLA @ 600V
75208A90A72A
112.5312A135A108A
150416A180A144A
225625A271A217A
300833A361A289A
5001,388A601A481A
7502,082A902A722A
10002,776A1,203A962A

Common Sizing Mistakes

  • Using connected load without demand factors — results in 30–50% oversizing
  • Forgetting the 125% motor factor — CEC requires it for the largest motor
  • Ignoring future capacity — adding EV charging, solar, or tenant loads later
  • Mixing kW and kVA — kVA = kW ÷ power factor (PF typically 0.85–0.90)
  • Not coordinating with the utility — transformer availability and lead times vary
Disclaimer: This article provides general engineering guidance for educational purposes. Always verify requirements against the current edition of the Canadian Electrical Code (CEC), Ontario Electrical Safety Code (OESC), and applicable standards. Consult a licensed Professional Engineer (P.Eng) for project-specific applications.

Need a Load Study or Capacity Assessment?

Our P.Eng team performs comprehensive electrical load studies, capacity assessments, and transformer sizing for buildings of any scale.

Get a Free Consultation