Load Calculations & Transformer Sizing: A Practical Guide

Section through a small office: two rooftop units with their disconnects on the roof, LED lighting, receptacles and a water heater inside, and the electrical room with the switchboard and a 150 kVA transformer.

An oversized transformer wastes capital and increases standby losses. An undersized one overheats, trips, and halts operations. Here's how to calculate electrical loads and size transformers correctly - with worked examples.

The Fundamentals

Connected Load vs. Demand Load

The connected load is the sum of all nameplate ratings of every piece of electrical equipment in a building. But not all equipment runs at the same time or at full capacity. The demand load accounts for this reality using demand factors.

Connected Load × Demand Factor = Demand Load
This is the actual load the electrical system must be designed to carry.

Demand Factor

The demand factor is the ratio of the maximum demand to the total connected load. It is often less than 1.0 where code demand factors or actual non-coincident operation apply. For example, a building with 100kVA connected lighting but only 80kVA running simultaneously has a demand factor of 0.80.

In the CEC, Rule 8-200 is the method for single dwellings; other occupancies use Rule 8-210 with Table 14. The CEC also sets factors for specific load types:

Load Type CEC Rule Typical Demand Factor
Electric heatingRule 62-11875-100%
Motors (largest)Rule 28-108125%
Motors (all others)Rule 28-108100%

Diversity Factor

The diversity factor accounts for the probability that not all circuits will be at peak simultaneously. It applies when combining multiple feeders or sub-panels:

Diversity Factor = Sum of individual maximum demands / Maximum demand of the whole system
Diversity factor is typically greater than or equal to 1.0 when individual peak demands do not occur at the same time. Do not assume 1.0 unless the loads are fully coincident.

Worked Example: Small Commercial Building

Illustrative estimate, not the CEC Rule 8-210 method: the unit loads and demand factors below are assumptions for illustration. Let's size the transformer for a 5,000 sq ft office building:

Step 1: Calculate Connected Loads

Load Calculation VA
General lighting5,000 sqft × 15 VA/sqft75,000
Receptacles5,000 sqft × 10 VA/sqft50,000
HVAC (RTU #1)25 kVA nameplate25,000
HVAC (RTU #2)15 kVA nameplate15,000
Water heater5 kW5,000
Total connected170,000

Step 2: Apply Demand Factors

Load Connected Demand Factor Demand VA
Lighting (first 10kVA)10,000100%10,000
Lighting (remaining)65,00075%48,750
Receptacles (first 10kVA)10,000100%10,000
Receptacles (remaining)40,00070%28,000
HVAC (largest motor - 125%)25,000125%31,250
HVAC (other motors)15,000100%15,000
Water heater5,000100%5,000
Total demand148,000

Step 3: Size the Transformer

Total demand = 148 kVA. Standard transformer sizes are: 75, 112.5, 150, 225, 300, 500, 750, 1000 kVA.

Select the next standard size up: 150 kVA transformer.

Engineering Judgment: Some engineers apply an additional 20-25% future capacity allowance. In this case, 148 × 1.25 = 185 kVA, which would push the selection to a 225 kVA transformer. This is a cost-benefit decision the client should be involved in.

From connected load to the transformer size

The article’s 5,000 sq ft office example, not a specific building. Equipment is drawn larger than scale.

From connected load to the transformer sizeSection through a single-storey office of 5,000 square feet. On the roof stand two packaged rooftop units on curbs, RTU 1 at 25 kVA and RTU 2 at 15 kVA, each with a fused disconnect connected by flexible conduit. Inside, LED troffers light the office, receptacles run along the wall behind two workstations, and a 5 kW water heater stands beside the electrical room. In the electrical room a dry-type transformer and a switchboard feed conduits that rise through the ceiling space to the rooftop units. A card shows the result of the worked example: 170 kVA connected, 148 kVA demand, next standard size 150 kVA.ONOFFONOFFDEMAND → TRANSFORMERConnected load170 kVADemand load148 kVANext standard size150 kVA1234567RTU #1 · 25 kVARTU #2 · 15 kVA5 kWLED LIGHTINGRECEPTACLES150 kVA

Parts

  1. General lighting: 5,000 sq ft × 15 VA/sq ft = 75,000 VA connected; first 10 kVA at 100 %, the remaining 65 kVA at 75 % → 58,750 VA demand.

  2. Receptacles: 5,000 sq ft × 10 VA/sq ft = 50,000 VA; first 10 kVA at 100 %, the remaining 40 kVA at 70 % → 38,000 VA.

  3. RTU #1, 25 kVA: the largest motor load, taken at 125 % → 31,250 VA. Rule 28-108

  4. RTU #2, 15 kVA: the other motor loads at 100 % → 15,000 VA. Rule 28-108

  5. Water heater, 5 kW: at 100 % → 5,000 VA.

  6. Transformer: 148 kVA demand → the next standard size up, 150 kVA. With a 20–25 % future allowance, 148 × 1.25 = 185 kVA → 225 kVA (a cost decision with the client).

  7. Switchboard and feeders are sized from the demand load, not the 170 kVA connected load.

Illustrative estimate from the article, not the CEC Rule 8-210 method: the unit loads and demand factors are assumptions. kVA = kW ÷ power factor.

  • Feeders in conduit
  • Liquid-tight flexible conduit
  • Nameplate load
  • Selected transformer
Figure 1. Connected load × demand factors = demand load, and the transformer is the next standard size above it.Sources: CEC Rules 8-210, 28-108 · the article’s worked example

Figure 1. From connected load to the transformer size

The kVA Formula

The fundamental relationships you need:

Single Phase:

kVA = (V × I) / 1,000

Three Phase:

kVA = (V × I × √3) / 1,000

Current from kVA (Three Phase):

I = kVA × 1,000 / (V × √3)

Quick Reference: Transformer Full Load Amps

Transformer kVA FLA @ 208V FLA @ 480V FLA @ 600V
75208A90A72A
112.5312A135A108A
150416A180A144A
225625A271A217A
300833A361A289A
5001,388A601A481A
7502,082A902A722A
10002,776A1,203A962A

Common Sizing Mistakes

  • Using connected load without demand factors - results in significant oversizing
  • Forgetting the 125% motor factor - CEC requires it for the largest motor
  • Ignoring future capacity - adding EV charging, solar, or tenant loads later
  • Mixing kW and kVA - kVA = kW ÷ power factor (PF typically 0.85-0.90)
  • Not coordinating with the utility - transformer availability and lead times vary

Planning a factory expansion or adding major equipment?

See how ETEM assesses industrial loads, transformers, switchboards, MCCs, feeders and service capacity before construction. Read the detailed factory expansion and industrial power-upgrade guide.

Explore Industrial Electrical Capacity Studies →

Frequently Asked Questions

What is the difference between connected load and demand load?

Connected load is the sum of all equipment nameplate ratings. Demand load applies CEC demand factors to reflect that not all equipment runs simultaneously. Always use demand load for service sizing.

How do I size a transformer for a commercial building?

Calculate total demand load using CEC demand factors, then select the next standard transformer size up (75, 112.5, 150, 225, 300, 500, 750, or 1000 kVA). Consider 20-25% future capacity.

What is the CEC 125% motor rule?

CEC Rule 28-108 requires conductors supplying two or more motors to have an ampacity of at least 125% of the full-load current of the largest motor plus 100% of the full-load current of all other motors.

Related service

Electrical engineering

ETEM can review existing electrical capacity, distribution constraints and proposed loads to define the required design and upgrade scope. When the calculation identifies constrained distribution, our Ontario panel-upgrade guide explains the next engineering checks.

Electrical engineering