HVAC Electrical Coordination: VFDs, Motor Controls & Why the Mechanical Schedule Is Never Enough

One-line diagram: motor control centre feeding two VFDs, a starter and a packaged unit with its disconnect, BAS control wiring, and the mechanical schedule data the electrical design depends on

The mechanical engineer provides a schedule: "RTU-1: 10 HP, 575V, 3-phase." That's where most coordination ends - and where most problems begin. Motor electrical requirements go far beyond horsepower and voltage. Here's what the electrical engineer actually needs to design a reliable HVAC power system.

What the Mechanical Schedule Doesn't Tell You

A typical HVAC equipment schedule lists voltage, phase, and horsepower. But the electrical design needs much more:

Mechanical Provides Electrical Actually Needs Why It Matters
10 HP, 575V, 3ΦMCA (Minimum Circuit Ampacity)Determines conductor size
10 HP, 575V, 3-phaseMOP (Maximum Overcurrent Protection)Determines breaker size
10 HP, 575V, 3-phaseFLA (Full Load Amps)Required for VFD sizing
10 HP, 575V, 3-phaseLRA (Locked Rotor Amps)Affects voltage drop during startup
10 HP, 575V, 3-phaseSCCR (Short Circuit Current Rating)Must exceed available fault current
10 HP, 575V, 3-phaseDisconnect requirementsCEC requires visible disconnect within sight of motor

VFD Sizing - It's Not Just About Horsepower

Variable Frequency Drives (VFDs) are now standard on most HVAC fans and pumps for energy savings. But sizing a VFD involves more than matching the motor HP:

Parameter Rule Example (10 HP @ 575V)
Motor FLAFrom motor nameplate or CEC Table 4410A
VFD output currentMust be motor FLA 10A continuous
VFD input currentTypically 1.0-1.2" output (due to harmonics)~12A
Input conductor sizingBased on VFD input current, not motor FLA#12 AWG (for 12A @ 75°C)
Input protectionPer VFD manufacturer - typically 150-175% of input current20A breaker
Common mistake: Sizing the VFD input breaker based on motor MOP. VFDs have their own overcurrent protection requirements specified by the manufacturer - these are almost always smaller than motor-direct MOP values. Using motor MOP on a VFD circuit violates the VFD listing.

Disconnect Requirements (CEC Rules 28-602 and 28-604)

The CEC requires a disconnecting means for every motor - but the details are where installations go wrong:

  • Within sight of the equipment - the disconnecting means must be within sight of the equipment it serves (Rule 28-604)
  • For rooftop units: disconnect must be on the roof, adjacent to the unit - a breaker in the basement panel doesn't count
  • Disconnect must be lockable in the open position for LOTO compliance
  • For VFD-supplied motors: disconnect within sight of both the VFD and the motor (Rule 28-604)

Typical HVAC Equipment Power Requirements

Equipment Type Typical Size Range Voltage Special Requirements
Rooftop Unit (RTU)3-25 HP supply fan, 30-150 kW heating575V or 347/600VMCA/MOP on nameplate; economizer controls
Chiller50-500 HP compressor575VReduced voltage starting (VFD or soft starter); high LRA
Boiler50-500 kW (gas/electric)120V controls, 575V elementsSeparate control transformer; gas interlock
Make-Up Air Unit (MAU)5-50 HP fan, 100-500 kW heating575VHigh heating loads affect transformer sizing
Exhaust Fan0.5-15 HP575V or 347VOften VFD-controlled for kitchen/lab exhaust
Circulation Pump1-25 HP575VVFD standard for variable flow systems

Coordination Meeting Checklist

To avoid costly field changes, electrical and mechanical engineers must coordinate on these items during design:

  • Final equipment schedule with MCA, MOP, FLA, LRA for every motor
  • VFD vs. across-the-line starting for each motor - affects conductor sizing and protection
  • Control voltage requirements (24V, 120V) and who provides the control transformer
  • Interlock wiring - fire alarm shutdown, BAS connections, smoke detector interlocks
  • Emergency power - which HVAC equipment goes on generator (stairwell pressurization, smoke exhaust)
  • Roof penetration locations for power feeds to RTUs and exhaust fans

Frequently Asked Questions

Why is HVAC coordination critical?

Mechanical schedules miss MCA, MOP, inrush data. Without coordination: undersized feeders and failed inspections. See our MCA/MOP guide.

How to size a VFD for HVAC?

Based on motor FLA, not HP. Add 15-25% overload. Input current 10-15% higher. Use VFD-rated cable.

CEC disconnect rules for HVAC?

CEC 28-602 and 28-604: within sight of the equipment, lockable, rated for locked rotor current. VFD: within sight of both VFD and motor.

Related service

Integrated MEP

ETEM can coordinate electrical and mechanical requirements with equipment, rooms and architectural constraints to define a practical engineering scope. Architecture-led teams can also review our MEP consultant workflow for architects.

Integrated MEP