HVAC Electrical Coordination: What the Electrical Design Needs from the Mechanical Schedule

Roof and plant room: a rooftop unit on its curb with a lockable fused disconnect beside it, an exhaust fan with its own disconnect, feeders through the roof from the panel below, a VFD, the BAS panel and the fire alarm panel.

The electrical design of a building's HVAC depends on data only the mechanical design can supply: each unit's electrical ratings, voltage and phase, where it sits, what must keep running in an emergency and what it interlocks with. When that data arrives late or wrong, feeders, breakers and disconnects are sized twice. This checklist sets out what the electrical engineer needs, and when.

What does the electrical engineer need from the mechanical schedule?

The mechanical equipment schedule is the electrical design's input. For every motor-driven or electrically heated item, the electrical engineer needs:

  • Voltage and phase (for example 600 V three-phase or 208 V single-phase), matched to what the building's distribution offers.
  • The electrical ratings from the nameplate. For packaged HVAC equipment that is the minimum circuit ampacity (MCA) and the maximum overcurrent protection (MOP). For a motor-compressor, the Ontario Electrical Safety Code bases the conductors on the marked rated load current (Rule 28-706). Where equipment is marked with a maximum overcurrent rating, that rating is binding (Rule 28-202). How these values become a wire and a breaker size is the subject of our MCA and MOP guide.
  • Horsepower or full-load current for separately supplied motors, and whether each one is on a variable-frequency drive. A VFD changes what the circuit is sized for.
  • Electric heat: duct heaters, unit heaters and electric reheat stages, with their kW and steps.
  • Location: roof, mechanical room, ceiling space, so the routes, the disconnects and the receptacles can be placed.
  • Controls power: who supplies 120 V to controllers, actuators and the building automation panels.

Ask for the data per selected unit, not per basis-of-design product, and ask again after the contractor's submittal. A substituted rooftop unit with a higher MOP can make an installed breaker the wrong size.

Where must disconnects and receptacles go?

The Code requires a separate disconnecting means for each motor branch circuit, each motor starter or controller and each motor (Rule 28-600). For air-conditioning and refrigeration equipment the motor disconnecting means must be within sight of and within 3 m of the equipment (Rule 28-604 5)). A breaker in a basement panel does not meet that for a rooftop unit. For a hermetic motor-compressor, the disconnect's continuous current rating must be at least 115 % of the compressor's rated load current (Rule 28-714 1)).

Rooftop HVAC equipment also brings a receptacle. Where heating, air-conditioning or refrigeration equipment is installed on a rooftop other than at a dwelling unit, at least one receptacle is provided for its maintenance (Rule 2-316). Rule 26-710 then sets what that receptacle is: Class A GFCI protected, on a separate branch circuit, CSA configuration 5-20R, within 7.5 m of the equipment and at least 750 mm above the roof.

What the electrical design needs from the mechanical schedule

A typical rooftop unit and exhaust fan adapted from draft workbench figures, not a design. The card shows the sizing steps, not values.

What the electrical design needs from the mechanical scheduleSection through a roof and the plant room below. A rooftop unit sits on its curb with a fused disconnect on a strut stand beside it, connected by flexible conduit; its supply duct drops into the building with a duct smoke detector. An upblast exhaust fan has its own disconnect on the roof and is fed from a VFD in the room below. Feeders run in conduit from the panel up through roof penetrations. A BAS panel with a control transformer sends dashed control lines to the units, the duct smoke detector signals the fire alarm panel, and a transfer switch serves a fan on emergency power. A card lists the VFD sizing steps: the motor full-load current, a VFD output at least that current, the drive’s input current, the input conductors, and the breaker per the VFD manufacturer.ONOFFONOFFVFD SIZING · THE STEPSMotor full-load currentfrom the CodeVFD output≥ motor FLAVFD input currentdrive dataInput conductorsfrom inputBreakerper VFD makerRTU · MCA / MOP on nameplateFANon generator12345678

Electrical points

  1. Equipment data: MCA (conductors), MOP (breaker), FLA (VFD sizing), LRA (starting voltage drop) and SCCR (above the available fault current) for every motor, not only HP and voltage.

  2. Disconnect on the roof: within sight of and within 3 m of the unit; a breaker in the basement panel does not count. Rule 28-604 5)

  3. VFD-supplied motor: the disconnect location is set in the design for both the drive and the motor.

  4. VFD circuit: conductors and protection sized from the drive’s input data and the manufacturer’s instructions.

  5. Roof penetrations: locations for the power feeds to RTUs and exhaust fans coordinated before construction.

  6. Interlocks: fire alarm shutdown, smoke detector interlocks and BAS connections.

  7. Control voltage: the control voltage, and who provides the control transformer.

  8. Emergency power: which HVAC equipment goes on the generator: the fans the Building Code requires in high buildings, and the owner’s choices.

  • Feeders in conduit
  • Motor circuit
  • Fire alarm interlock
  • BAS control
Figure 1. Horsepower and voltage are not enough: the electrical design needs the nameplate currents, ratings, disconnect locations, controls and emergency loads.Sources: OESC Rules 2-316, 26-710, 28-600, 28-604, 28-706 · OBC 3.2.7.9 · VFD manufacturers’ data

Figure 1. What the electrical design needs from the mechanical schedule

Which mechanical loads need emergency power?

The Building Code decides some of this, not the owner. Division B, Article 3.2.7.9 requires an emergency power supply that can run under full load for at least 2 hours, from an emergency generator, for: every elevator serving storeys above the first storey in a building more than 36 m high; equipment that supplies water for fire suppression where that supply depends solely on electrical power, such as an electric fire pump; the fans and other equipment that maintain the air quality required in high buildings, and the fans required for venting them; and the fans required for openings through floor assemblies in high buildings. The generator installation itself follows CSA C282 (Article 3.2.7.5).

Beyond the code minimum, the owner decides what else stays on: heating in a building that must not freeze, a server room's cooling, process cooling. Each of those choices adds generator capacity, and each one belongs in the mechanical schedule as "on emergency power: yes or no". Our guide to commercial emergency generator replacement covers the generator side.

What does a coordination checklist look like?

ItemMechanical providesElectrical designsCode point
Equipment ratingsMCA/MOP or rated load current, voltage, phase, per selected unitConductor and overcurrent sizes, panel capacityRules 28-706, 28-202
DisconnectsUnit locations and access sidesDisconnect type, rating and positionRules 28-600, 28-604 5), 28-714
Rooftop receptacleRooftop equipment locationsGFCI 5-20R receptacle on its own circuit within 7.5 mRules 2-316, 26-710
Emergency powerLoads that must run on the generatorGenerator sizing, transfer and distributionOBC 3.2.7.9; CSA C282
VFDsWhich motors, drive location, bypassSupply to the drive, motor circuit, disconnect locationSection 28
InterlocksFire alarm shutdown, smoke control sequence, BAS pointsFire alarm and control wiringProject fire safety design
RevisionsSubmittal data for substituted equipmentRecheck of every affected circuitRule 28-202 (marked ratings)

When should each piece of data arrive?

The order matters more than the format. At schematic design, the electrical engineer needs the main loads and their locations, so the service and the main distribution are sized once. At design development, the equipment schedule with preliminary electrical data and the emergency power list. At contract documents, the final schedule, the controls power and the interlock list. During construction, the contractor's submittals, checked against the circuits already designed. The same discipline applies to replacement projects, where the existing circuit often decides what equipment fits; see the chiller replacement guide for a large example.

What is specific to Ontario?

  • The Electrical Safety Code, not the Building Code, sets the circuit, disconnect and receptacle rules above. The Building Code sets the emergency power for life-safety loads.
  • ESA inspects the electrical installation, under its own notification, separate from the building permit for the HVAC work; see our guide to HVAC design for a building permit for the mechanical side.
  • One project team. Our integrated MEP service puts the mechanical schedule and the electrical design in one workflow, so the data above is coordinated before it reaches the drawings.

Frequently Asked Questions

Where must the disconnect for a rooftop unit be?

Within sight of and within 3 m of the equipment, under Rule 28-604 5) of the Ontario Electrical Safety Code. A breaker in a remote panel does not replace it.

Does rooftop HVAC equipment need a receptacle?

Yes, other than at a dwelling unit. Rule 2-316 requires at least one receptacle for maintenance, and Rule 26-710 makes it a Class A GFCI-protected 5-20R on a separate branch circuit, within 7.5 m of the equipment and at least 750 mm above the roof.

Which HVAC loads must be on emergency power?

The Building Code requires at least 2 hours of generator power for elevators serving upper storeys in buildings more than 36 m high, fire-suppression water supply that depends solely on electricity, and the air-quality and venting fans required in high buildings. Anything beyond that is the owner's choice.

Why do substituted units cause electrical problems?

Marked overcurrent ratings on equipment are binding under Rule 28-202. A substitute with a different MCA or MOP can need a different conductor or breaker than the one already installed, so every submittal is checked against the circuit.

Sources

  1. Ontario Electrical Safety Code, 29th edition, Rules 2-316, 26-710, 28-202, 28-600, 28-604, 28-706 and 28-714.
  2. Ministry of Municipal Affairs and Housing, 2024 Building Code Compendium, Division B, Part 3, Articles 3.2.7.5 and 3.2.7.9.
  3. O. Reg. 163/24, Building Code.

Related service

Integrated MEP

ETEM can coordinate electrical and mechanical requirements with equipment, rooms and architectural constraints to define a practical engineering scope. Architecture-led teams can also review our MEP consultant workflow for architects.

Integrated MEP