HVAC Electrical Coordination: VFDs, Motor Controls & Why the Mechanical Schedule Is Never Enough

Roof and plant room: a rooftop unit on its curb with a lockable fused disconnect beside it, an exhaust fan with its own disconnect, feeders through the roof from the panel below, a VFD, the BAS panel and the fire alarm panel.

The mechanical engineer provides a schedule: "RTU-1: 10 HP, 575V, 3-phase." That's where most coordination ends - and where most problems begin. Motor electrical requirements go far beyond horsepower and voltage. Here's what the electrical engineer actually needs to design a reliable HVAC power system.

What the Mechanical Schedule Doesn't Tell You

A typical HVAC equipment schedule lists voltage, phase, and horsepower. But the electrical design needs much more:

Mechanical Provides Electrical Actually Needs Why It Matters
10 HP, 575V, 3ΦMCA (Minimum Circuit Ampacity)Determines conductor size
10 HP, 575V, 3-phaseMOP (Maximum Overcurrent Protection)Determines breaker size
10 HP, 575V, 3-phaseFLA (Full Load Amps)Required for VFD sizing
10 HP, 575V, 3-phaseLRA (Locked Rotor Amps)Affects voltage drop during startup
10 HP, 575V, 3-phaseSCCR (Short Circuit Current Rating)Must exceed available fault current
10 HP, 575V, 3-phaseDisconnect requirementsCEC requires visible disconnect within sight of motor

VFD Sizing - It's Not Just About Horsepower

Variable Frequency Drives (VFDs) are now standard on most HVAC fans and pumps for energy savings. But sizing a VFD involves more than matching the motor HP:

Parameter Rule Example (10 HP @ 575V)
Motor FLAFrom motor nameplate or CEC Table 4411A
VFD output currentMust be ≥ motor FLA11A continuous
VFD input currentTypically 1.0-1.2 × output (due to harmonics)~12A
Input conductor sizingBased on VFD input current, not motor FLA#12 AWG (for 12A @ 75°C)
Input protectionPer VFD manufacturer - typically 150-175% of input current20A breaker
Common mistake: Sizing the VFD input breaker based on motor MOP. VFDs have their own overcurrent protection requirements specified by the manufacturer - these are almost always smaller than motor-direct MOP values. Using motor MOP on a VFD circuit violates the VFD listing.

What the electrical design needs from the mechanical schedule

A typical rooftop unit and exhaust fan adapted from draft workbench figures, not a design. Sizes from the article’s example.

What the electrical design needs from the mechanical scheduleSection through a roof and the plant room below. A rooftop unit sits on its curb with a fused disconnect on a strut stand beside it, connected by flexible conduit; its supply duct drops into the building with a duct smoke detector. An upblast exhaust fan has its own disconnect on the roof and is fed from a VFD in the room below. Feeders run in conduit from the panel up through roof penetrations. A BAS panel with a control transformer sends dashed control lines to the units, the duct smoke detector signals the fire alarm panel, and a transfer switch serves the stairwell pressurization fan on emergency power. A card works the article’s VFD example: 10 HP at 575 V, FLA 11 A from CEC Table 44, VFD output at least the FLA, input about 12 A, number 12 AWG input conductors and a 20 A breaker per the VFD manufacturer.ONOFFONOFFVFD SIZING · 10 HP AT 575 VMotor FLA (CEC Table 44)11 AVFD output ≥ FLA11 AVFD input ≈ 1.0–1.2 × output~12 AInput conductors#12 AWGBreaker per VFD maker20 ARTU · MCA / MOP on nameplateSTAIR FANon generator12345678

Electrical points

  1. Equipment data: MCA (conductors), MOP (breaker), FLA (VFD sizing), LRA (starting voltage drop) and SCCR (above the available fault current) for every motor, not only HP and voltage.

  2. Disconnect on the roof: adjacent to the unit and within sight of it, lockable open; a breaker in the basement panel does not count. Rules 28-602, 28-604

  3. VFD-supplied motor: disconnect within sight of both the VFD and the motor. Rule 28-604

  4. VFD circuit: conductors from the VFD input current, protection per the VFD manufacturer (not the motor MOP, which can violate the listing).

  5. Roof penetrations: locations for the power feeds to RTUs and exhaust fans coordinated before construction.

  6. Interlocks: fire alarm shutdown, smoke detector interlocks and BAS connections.

  7. Control voltage: 24 V or 120 V, and who provides the control transformer.

  8. Emergency power: which HVAC equipment goes on the generator (stairwell pressurization, smoke exhaust).

  • Feeders in conduit
  • Motor circuit
  • Fire alarm interlock
  • BAS control
Figure 1. Horsepower and voltage are not enough: the electrical design needs the nameplate currents, ratings, disconnect locations, controls and emergency loads.Sources: CEC Rules 28-602, 28-604 · CEC Table 44 · VFD manufacturers’ data

Figure 1. What the electrical design needs from the mechanical schedule

Disconnect Requirements (CEC Rules 28-602 and 28-604)

The CEC requires a disconnecting means for every motor - but the details are where installations go wrong:

  • Within sight of the equipment - the disconnecting means must be within sight of the equipment it serves (Rule 28-604)
  • For rooftop units: disconnect must be on the roof, adjacent to the unit - a breaker in the basement panel doesn't count
  • Disconnect must be lockable in the open position for LOTO compliance
  • For VFD-supplied motors: disconnect within sight of both the VFD and the motor (Rule 28-604)

Typical HVAC Equipment Power Requirements

Equipment Type Typical Size Range Voltage Special Requirements
Rooftop Unit (RTU)3-25 HP supply fan, 30-150 kW heating575V or 347/600VMCA/MOP on nameplate; economizer controls
Chiller50-500 HP compressor575VReduced voltage starting (VFD or soft starter); high LRA
Boiler50-500 kW (gas/electric)120V controls, 575V elementsSeparate control transformer; gas interlock
Make-Up Air Unit (MAU)5-50 HP fan, 100-500 kW heating575VHigh heating loads affect transformer sizing
Exhaust Fan0.5-15 HP575V or 347VOften VFD-controlled for kitchen/lab exhaust
Circulation Pump1-25 HP575VVFD standard for variable flow systems

Coordination Meeting Checklist

To avoid costly field changes, electrical and mechanical engineers must coordinate on these items during design:

  • Final equipment schedule with MCA, MOP, FLA, LRA for every motor
  • VFD vs. across-the-line starting for each motor - affects conductor sizing and protection
  • Control voltage requirements (24V, 120V) and who provides the control transformer
  • Interlock wiring - fire alarm shutdown, BAS connections, smoke detector interlocks
  • Emergency power - which HVAC equipment goes on generator (stairwell pressurization, smoke exhaust)
  • Roof penetration locations for power feeds to RTUs and exhaust fans

Frequently Asked Questions

Why is HVAC coordination critical?

Mechanical schedules miss MCA, MOP, inrush data. Without coordination: undersized feeders and failed inspections. See our MCA/MOP guide.

How to size a VFD for HVAC?

Based on motor FLA, not HP. Add 15-25% overload. Input current 10-15% higher. Use VFD-rated cable.

CEC disconnect rules for HVAC?

CEC 28-602 and 28-604: within sight of the equipment, lockable, rated for locked rotor current. VFD: within sight of both VFD and motor.

Related service

Integrated MEP

ETEM can coordinate electrical and mechanical requirements with equipment, rooms and architectural constraints to define a practical engineering scope. Architecture-led teams can also review our MEP consultant workflow for architects.

Integrated MEP