EV Charging in Ontario Condos: How Boards Handle Owner Applications and the Electrical Capacity Study They Need
Since 1 May 2018, Ontario condominium corporations have had a defined process for electric vehicle charging: an owner can apply to install a charger, the board has 60 days to answer, and it may refuse only on narrow technical grounds backed by a professional's report. That puts one question in front of every board and property manager: does the building have the electrical capacity, and how is it shared fairly? This guide explains the rules, what an electrical capacity study covers, and how an energy management system lets most buildings say yes without a service upgrade.
What the Condominium Act Requires
The rules sit in Ontario Regulation 48/01 under the Condominium Act, 1998, in the sections on electric vehicle charging systems added in 2018. The Condominium Authority of Ontario (CAO) publishes a guide and template forms for both routes: an installation proposed by the corporation, and one requested by an owner. In both cases the work is carried out by a Licensed Electrical Contractor under an Electrical Safety Authority (ESA) permit, with a Certificate of Acceptance when it is done, and ESA's checklist for boards asks whether the building's load capacity has been confirmed with the utility and, for buildings older than ten years, asks the board to consider the electrical systems in place.
That is the link between the legal process and the engineering. The regulation does not require an engineer's report before an owner can be told yes, but it effectively requires one before an owner can be told no.
Owner Applications: The 60-Day Clock
An owner's application must be in writing, signed, identify the owner and an address for service, and include drawings, specifications or information about the proposed installation. From there:
- The board must respond within 60 days, or another period agreed with the owner in writing.
- It can reject the application only with a report from a qualified professional stating that the installation would be contrary to an Act, including the Electrical Safety Code; would adversely affect the structural integrity of the corporation's property; or would pose a serious risk to health and safety or damage the property. A copy of the report goes to the owner.
- It may instead require an alternative location or manner of installation, but only where that is needed so the installation would not result in a material reduction or elimination of other owners' use and enjoyment of the property, would not contravene the declaration, by-laws or rules, and would not be contrary to an agreement the corporation is party to. The alternative must not cause the owner unreasonable costs.
- Silence is not a refusal. No response within 60 days is treated as neither rejecting the application nor requiring an alternative.
- An agreement follows within 90 days of acceptance, covering how the installation is done, who pays for what, use, operation, repair, maintenance and insurance, ownership of the equipment, the cost of preparing and registering the agreement, and how it ends. The corporation registers it on title, and it takes effect only when registered.
- Costs and disputes. Unless agreed otherwise, the owner pays for the installation, whether the owner or the corporation carries it out, and may also carry electricity and maintenance. Disputes go to mediation and arbitration, generally within six months of a rejection or of the 90-day agreement period passing without an agreement.
Read together, these rules make the electrical assessment the board's main tool. "The service is full" is a valid reason to require a load-managed charger as the alternative manner of installation, or, if a professional confirms that connection would breach the Electrical Safety Code, a valid ground for rejection. "We have not checked" is neither.
Board-Initiated Installations
A corporation can also install charging on the common elements itself, for example a shared bank of chargers. Under the CAO guide the board can proceed without an owner vote when the estimated cost is not more than 10 per cent of the annual budgeted common expenses and owners would not see a material reduction of their use or enjoyment: it sends owners a notice describing the installation, the estimated cost and how it will be paid for, and may proceed once 60 days have passed. The costs are common expenses. The same Condominium Act rules on repair, the reserve fund and changes to the common elements apply to other building systems; our condo boiler replacement guide sets them out for the heating plant.
The Real Question: Is There Capacity?
Every condominium was designed around the loads of its time: suite panels, corridor and parking lighting, elevators, pumps, HVAC, plus a margin. Level 2 charging adds a load that is large per vehicle, that peaks in the evening when the building already peaks, and that grows as more owners buy EVs. A 7.2 kW charger draws about 30 A at 240 V. In ESA's worked example for an 18-unit apartment building, seven Level 2 chargers with no load management add 224 A at 100 per cent of their rating, because that is how the Electrical Safety Code counts chargers without an energy management system; as a continuous load, that ties up about 280 A of service capacity. Scale that to a 200-unit tower and the arithmetic explains why boards hesitate. The answer is not to guess: the capacity question has a defined method.
What the Capacity Study Covers
- The existing service and distribution: service size and voltage, main switchgear, utility transformer, riser and parking-level feeders, spare panel capacity. A single-line diagram is drawn or updated; most older buildings lack a current one.
- Measured demand. For an existing installation the Electrical Safety Code lets a qualified person, which ESA defines to include a professional engineer, base the calculation on the building's demonstrated load rather than the full calculated load, within the conditions of the rule. The utility can provide twelve months of interval data; that measured peak, with the allowance ESA applies on top of it, is the honest baseline for how much of the service is really in use. Which method applies to a given building is part of the study.
- The charging scenarios: how many spaces now, in five and in ten years, and at what charging power. ESA's multi-residential guidance tells boards to plan for the future state, not the first application.
- The code calculation under Section 8, with and without an energy management system, and the resulting service and feeder loading.
- The physical route: where new panels sit, how feeders reach the parking levels, and the mechanical protection ESA's bulletin accepts in a garage (a 1 m clearance from vehicles; a raised curb with the charger set 1 m back from the curb face; curb stops at least 10 cm high and 15 cm wide; the bottom of the charger at least 1 m above the floor; or bollards set at least 1.5 m below grade and not in asphalt alone).
- Options and costs for the building, the utility and the owners, so that the board can choose with the numbers in front of it.
The study is the "report from a qualified professional" the regulation refers to. It also gives the board a defensible basis for any alternative it proposes, and a long-term plan rather than a one-charger decision repeated twenty times.
How EVEMS Changes the Math
An electric vehicle energy management system (EVEMS) monitors the electrical system and controls the chargers so that their combined draw never exceeds a set limit. ESA's bulletin on electric vehicle charging systems summarizes how the Code treats it:
- Under Rule 8-106(10), where chargers are controlled by an energy management system, their demand load is limited to the maximum load the system allows.
- Under Rule 8-106(11), where the system monitors the consumer's service and feeders and controls the chargers, the charging demand need not be included in the calculated load at all.
- Under Rule 86-300, each charger normally needs its own branch circuit, but a charger may share a branch circuit with other loads where an energy management system is installed, and such systems are permitted in any type of occupancy.
- An adjustable charger counts as an energy management system only if it has the system's monitoring and control features; a charger simply set to a lower current does not.
For a condominium this is decisive. A building whose measured peak leaves, say, 150 A of headroom can support far more than five chargers if the system caps the group at that headroom and shares it among the vehicles plugged in; most cars sit in the garage overnight and need only a few hours of charge. The board gets a yes for the first applicant and a scalable plan for the next twenty, without touching the utility service. Our guide to EVEMS explains the systems in more detail.
Some design details affect which products are acceptable: a separate disconnecting means for chargers rated over 60 A or over 150 V to ground; adjustable chargers fixed in place, set per the manufacturer, permanently marked and with restricted access to the adjustment; and separate protection rules for receptacle-based installations in dwelling units.
From application to yes
The owner-application route under O. Reg. 48/01 and where the electrical design connects. Not a legal opinion.
Electrical points
Owner application: in writing, signed, identifying the owner and an address for service, with drawings, specifications or information about the proposed installation.
60-day clock: the board responds within 60 days or another period agreed in writing; it may reject only with a report from a qualified professional.
Capacity study: the existing service and distribution, twelve months of interval data from the utility (the demonstrated load, with the allowance ESA applies on top of it) and the charging scenarios now, in five and in ten years.
Headroom, EVEMS group limit: where chargers are controlled by an energy management system, their demand load is limited to the maximum load the system allows; where the system monitors the service and feeders and controls the chargers, the charging demand need not be included in the calculated load at all. Rule 8-106(10), (11)
No headroom, service upgrade: a service upgrade request through the utility’s connection process; Toronto Hydro asks for low-voltage requests three months to three years in advance.
Registered agreement: within 90 days of acceptance; the corporation registers it on title, and it takes effect only when registered.
ESA permit: the work is carried out by a Licensed Electrical Contractor under an ESA permit, with a Certificate of Acceptance when it is done.
A separate disconnecting means for chargers rated over 60 A or over 150 V to ground. Rule 86-304
- Path to approval
- Utility upgrade (last resort)
Three Paths for an Existing Building
| Path | When it fits | What it involves |
|---|---|---|
| 1. Load-managed charging on the existing service | Measured demand shows headroom; the owners want charging soon. | EVEMS with a group limit set from the study; new distribution to the parking levels; chargers added space by space under the system. No utility upgrade. |
| 2. Service or transformer upgrade | Headroom is small, or the building wants unmanaged charging at many spaces. | A service upgrade request to the utility, new main gear and feeders; long lead times and significant cost; usually combined with path 1. |
| 3. EV-ready infrastructure first | The building wants to avoid repeat construction and spread cost. | Conduit, cable tray and panel space to every parking area now; chargers later as owners apply. Often paired with path 1. |
Most buildings we see land on path 1, with path 3 as the way the common-element work is organized so that each later installation is a short, inexpensive job. Path 2 is the last resort, not the first assumption.
The Utility Side
In Toronto, Toronto Hydro's Load Capacity Map shows estimated available capacity on its stations and feeders. It is updated about quarterly, is explicitly illustrative and does not replace engineering studies, excludes smaller stations and lower-voltage feeders, and says nothing about cost. For a condominium it is useful for one thing: a feeder in the lowest band is a warning that a service upgrade may need work on the utility's side.
Where a building does need more supply, the request is a service upgrade through the utility's connection process. Toronto Hydro asks for low-voltage requests three months to three years in advance and high-voltage requests at least six months and up to five years ahead, collects a design deposit through a job quotation on projects with technical elements, and, for residential customers, charges costs above the basic connection to the customer. Those lead times are why the capacity study comes first: a board that discovers it needs an upgrade in month two of a 60-day clock has no good options. Our Toronto Hydro connection guide walks through the application; buildings outside Toronto follow the same logic with Alectra, Hydro One, Elexicon or their local distributor.
A Plan for the Board
- Commission the capacity study before the first application arrives, or the week it does, and give the engineer the utility account details so the demand data can be requested at once.
- Adopt an EV charging policy on the strength of the study: the group limit, the standard charger and system, the metering and cost-recovery model, and the standard agreement terms.
- Answer applications inside 60 days with one of the three responses the CAO templates provide: accepted, accepted with an alternative manner or location, or rejected with the professional's report attached.
- Build the common-element infrastructure once: the distribution to the parking levels and the energy management system. Each owner's installation then connects to it under the registered agreement.
- Keep the single-line diagram and the system's load records current, so the next application starts from facts.
Frequently Asked Questions
Can a condo board refuse an owner's EV charger application?
Only with a report from a qualified professional stating that the installation would be contrary to an Act such as the Electrical Safety Code, would affect the structural integrity of the property, or would pose a serious risk to health and safety or damage the property. Otherwise the board must accept it or require an alternative location or manner that does not impose unreasonable costs on the owner.
How long does the board have to respond?
60 days from receiving the application, unless the board and the owner agree to a different period in writing. If the board does not respond, it is treated as having neither rejected nor required an alternative.
Who pays for an owner-requested charger?
Unless the agreement says otherwise, the owner pays for the installation and may also be responsible for electricity and maintenance. The written agreement, registered on title, sets this out.
What is an electrical capacity study?
An engineer's assessment of the building's service, distribution and measured demand, the charging demand expected now and later, the code calculation with and without an energy management system, and the options. It is the professional report the regulation refers to and the basis for the board's EV policy.
Do we need a service upgrade to add EV charging?
Often not. The Electrical Safety Code lets an energy management system cap the charging load so that it fits within the building's measured headroom. A service upgrade is needed when the headroom is too small for the charging the owners want, and it takes months to years through the utility.
Does the Load Capacity Map tell us whether our building has capacity?
No. It shows the utility's estimated capacity on its own feeders and stations, not the capacity of your building's service. Your building's capacity comes from its service size, its measured demand and the code calculation in the capacity study.
Sources
- Condominium Authority of Ontario, CAO Guide on Electric Vehicles Charging Systems (11 April 2024) and the CAO online resource and templates; Ontario Regulation 48/01 under the Condominium Act, 1998.
- Electrical Safety Authority, Bulletin 86-1-7, Electric vehicle charging systems (May 2025); Bulletin 8-3-16, Maximum circuit loading and demand factors (May 2025); Guide to EV Charger Installation for Multi-Residential Buildings (2023).
- Ontario Electrical Safety Code (29th edition), Rules 8-106, 8-202, 8-500 and Section 86.
- Toronto Hydro, Load Capacity Map and FAQ; service connections and service upgrade requests.