Generator Sizing & Step Loading: Avoiding the #1 Emergency Power Mistake

A hospital's backup generator starts during a blackout. The ATS transfers life-safety loads. Then the HVAC kicks in - and the generator stalls. 200 patients are in the dark. The cause? The engineer sized the generator for running load but ignored step loading. Here's how to avoid this catastrophic mistake.

Generator Sizing and Step Loading

kW vs. kVA: The First Trap

Generators are rated in both kW (real power) and kVA (apparent power). These are NOT the same thing. The relationship is governed by power factor:

The Relationship:

kW = kVA - Power Factor (PF)

Typical Generator Rating:

500 kW / 625 kVA at 0.8 PF

A generator rated 500 kW can only deliver 500 kW even if the kVA demand is lower. If your load has a PF of 0.7, you need: kVA = 500/0.7 = 714 kVA, requiring a larger generator.

What is Step Loading?

Step loading is the practice of sequencing emergency loads onto the generator in planned stages rather than connecting everything simultaneously. This is critical because:

  • Motor starting current is 5-7" the running current. A 50HP motor runs at 65A but starts at 400A
  • Voltage dip during motor starting must stay within 15-20% or motors won't start and lights will visibly flicker
  • Frequency dip from sudden load application can cause the generator to stall if it exceeds the governor's recovery capability
The #1 rule of generator sizing: Never apply more than 50% of the generator's rated capacity in a single step. Most manufacturers recommend individual steps not exceeding 30% of rated kW.

Step Loading Sequence Example

For a 400 kW generator serving a 6-storey commercial building:

Step Time Delay Loads Connected Step kW Cumulative kW % of Gen
10 sec (immediate)Emergency lighting, fire alarm, exit signs25256%
210 secFire pump (jockey + main)7510025%
320 secElevators (one car at a time)4514536%
430 secStairwell pressurization fans6020551%
545 secCritical HVAC (server room cooling)8028571%
660 secSelected receptacles, BAS, security5534085%

Notice that no single step exceeds 80 kW (20% of generator capacity), and the largest motor load (fire pump at Step 2) is applied when the generator is lightly loaded, giving it maximum headroom for the starting transient.

CEC Section 46: Emergency Power Requirements

The Canadian Electrical Code, Section 46, defines the requirements for emergency power systems in buildings:

Requirement CEC Reference Key Detail
Emergency power sourceRule 46-202Rechargeable battery system or generator, with duration tied to building-code requirements
Automatic transfer controlRule 46-206Emergency power supply controlled by automatic transfer equipment upon normal supply failure
Emergency wiring methodsRule 46-108Life-safety conductors must use approved emergency wiring methods and separation where required
Overcurrent coordinationRule 46-208Emergency supply OCP must be coordinated with life-safety feeders and branch circuits
Transfer timing / fuel / testingOBC/NBC + CSA C282Confirm start time, fuel supply, room/exterior installation, maintenance, and load testing under the applicable building and generator standards
Unit equipmentRules 46-302 / 46-304Applies to emergency lighting unit equipment, not generator transfer-time requirements

Generator Sizing: The Complete Checklist

  • Running load: Sum of all continuous loads at their demand values (kW and kVA)
  • Starting load: Largest motor starting kVA in each step + running kVA of everything already connected
  • Altitude derating: Generators lose ~3.5% capacity per 1,000 ft above 500 ft elevation
  • Temperature derating: Above 40°C ambient, capacity drops ~2% per additional °C
  • Future growth: Typically 15-25% spare capacity for additional loads
  • Harmonic loads: UPS systems, VFDs, and LED drivers create harmonics that derate the alternator

Common Sizing Mistakes

  • Sizing for running load only - ignoring motor starting transients is the most common cause of generator stalling on transfer
  • No step loading sequence - connecting all loads simultaneously through a single ATS with no time delays
  • Confusing kW and kVA - a 500 kVA generator at 0.8 PF only delivers 400 kW. Specifying "500" without units leads to undersizing
  • Undersizing for UPS loads - UPS input current is non-linear. The generator alternator must be oversized by 1.5-2" for harmonic loads
  • No load bank testing - a generator that passes a monthly no-load test may still stall under real load. Annual load bank testing is essential

Frequently Asked Questions

What's the difference between kW and kVA?

kW is real power; kVA is apparent power. kVA = kW ÷ power factor (typically 0.8). A 100 kW generator is actually 125 kVA. Always size in kVA.

What is step loading?

The sequence in which loads are applied after generator startup. Motors cause 6-8x inrush currents. Proper sequencing prevents voltage/frequency dips. See our load calculation guide.

Does CEC require emergency generators?

CEC Section 46 governs emergency power wiring, control, and overcurrent protection where emergency power is required. Building triggers, duration, generator performance, fuel supply, and testing must also be checked against OBC/NBC and CSA C282. See our permit guide for compliance.

Disclaimer: This article provides general engineering guidance for educational purposes. Always verify requirements against the current edition of the Canadian Electrical Code (CEC), Ontario Electrical Safety Code (OESC), and applicable standards. Consult a licensed Professional Engineer (P.Eng) for project-specific applications.

Need a Generator Sizing Study?

ETEM Engineering performs comprehensive generator sizing, step loading analysis, and ATS coordination for hospitals, data centers, high-rises, and industrial facilities. We deliver code-compliant emergency power designs that work when it matters most.

Get a Free Consultation