Commercial Rooftop Solar PV Design in Ontario: Electrical Steps, Section 64 and Utility Connection

Commercial flat roof with three tilted rows of PV modules on racking, a combiner box and the DC conduit down to an inverter, an AC disconnect and the main switchboard in the electrical room below.

Designing a commercial rooftop solar PV system in Ontario means sizing strings and inverters to the Electrical Safety Code's Section 64, choosing where it connects to the building's service, and getting the utility's connection approval. Structural review of the roof is a separate engineering discipline. This guide covers the electrical design steps and the Ontario rules behind them.

What are the electrical design steps?

  1. Load and site data: twelve months of the building's consumption and demand, the service and switchboard ratings, the roof areas the structural engineer accepts, and the shading.
  2. Array and string design: modules in series set the string voltage; strings in parallel set the current. Both are checked at the site's temperature extremes.
  3. Inverter selection: the strings must land in the inverter's voltage window across the year, below its maximum dc input, and the inverter must be marked interactive.
  4. Protection and disconnects: overcurrent protection, dc arc-fault and ground-fault protection, disconnects and rapid shutdown, all rated for dc where they are on the dc side.
  5. Point of connection: supply side or load side of the service disconnect, and the busbar check that goes with a load-side connection.
  6. Marking, documents and approvals: labels and directories, the ESA notification and the utility's connection process.
Series vs Parallel PV Connections The same modules can create very different voltage and current conditions. Series string Voltage adds: Vtotal = V1 + V2 + V3 + V4 Current stays near one module/string current M1 M2 M3 M4 Parallel strings Current adds: Itotal = Istring1 + Istring2 + Istring3 Voltage stays near one string voltage Combiner String 1 String 2 String 3
Series strings drive voltage checks such as cold Voc and hot Vmp. Parallel strings drive current, conductor ampacity, combiner, and OCP checks.

How does Section 64 set the voltage and current?

Section 64 of the Ontario Electrical Safety Code covers renewable energy systems, energy production systems, energy storage systems and batteries. For PV the key ratings are:

  • Maximum voltage. The maximum PV source and output circuit voltage is the rated open-circuit voltage multiplied by 125 %, or, alternatively, calculated from the lowest expected ambient temperature and the module manufacturer's temperature coefficient (Rule 64-202). That voltage sets the rating of every dc component.
  • Voltage limits. Dwelling units are limited to 600 V dc. Other installations up to 1500 V dc may be exempted from certain high-voltage rules where they are serviced only by qualified persons, with the conditions of Rule 64-202 5).
  • Current. A PV source circuit is rated at not less than 125 % of its rated short-circuit current (Rule 64-206), and its overcurrent device is not larger than the conductor ampacity or the module's marked maximum, whichever is less (Rule 64-214).
  • Inverter output. The maximum current of the inverter output circuit is the inverter's continuous output rating (Rule 64-100).

From modules to the switchboard: strings, combiner, inverter and disconnects

A typical commercial rooftop system, not a design. Checks must use the actual datasheets and site temperatures.

From modules to the switchboard: strings, combiner, inverter and disconnectsA commercial flat roof with three tilted rows of PV modules on racking; each row is one string of modules in series, traced in orange, blue and green. The strings run in parallel to a combiner box with string fuses and a DC disconnect. DC conductors run in conduit down into the electrical room to a string inverter with an integral DC disconnect, then through an AC disconnect to the main switchboard. A green bonding conductor connects the module frames and racking.ONOFFString 1String 2String 3DC in conduitMAIN SWITCHBOARD1234567

Detail A: temperature checks

Cold Voc below the maximum DC rating; hot Vmp inside the MPPT window

Detail A: the two temperature checksA string-voltage scale with the inverter MPPT window shaded green and the maximum DC voltage marked red. The cold-weather open-circuit voltage must fall below the maximum DC rating, and the hot-weather operating voltage must fall inside the MPPT window. Schematic, no values.Max. DCMPPT windowCold VocHot VmpString voltage

Parts

  1. Strings: modules in series add voltage at about the same current; check cold Voc and hot Vmp with the module temperature coefficients.

  2. Combiner: parallel strings add current: string OCP, conductor ampacity, combiner ratings and a DC-rated disconnect.

  3. DC conductors: PV source and output conductors may be energized whenever modules see light; route, protect and mark them, with DC-rated equipment. Section 64

  4. Inverter: MPPT window, maximum DC voltage, maximum input current, DC/AC ratio within limits, anti-islanding and environmental rating.

  5. AC disconnect: isolation for service and emergency response, coordinated with the ESA and the distributor.

  6. Switchboard connection: at the main switchboard, a downstream board or upstream of the main: coordinated with OESC/CEC, the utility, service ratings and metering. Section 84

  7. Bonding: module frames, racking, raceways and enclosures bonded under CEC/OESC rules; DC arc-fault, rapid shutdown and permanent warning markings per Section 64. Rules 64-200, 64-216, 64-218

  • String 1
  • String 2
  • String 3
  • DC / AC conductors
  • Bonding
Figure 10. Series strings set the voltage, parallel strings set the current, and every device between the roof and the board must be rated for both.Sources: OESC/CEC Section 64 (Rules 64-200, 64-216, 64-218) · Section 84 · inverter and module manufacturers’ data

Figure 10. From modules to the switchboard: strings, combiner, inverter and disconnects

What protection does a rooftop system need?

TopicRequirementRule
dc arc-fault protectionSystems with a dc source or output circuit of 80 V or more are protected by a dc arc-fault circuit interrupter64-216
Ground-fault protectionA device or system that detects a ground fault, indicates it and controls the faulted circuit64-066
Rapid shutdownRequired on or in buildings where PV conductors run more than 1 m from the array; those conductors reduced to not more than 30 V within 30 s of initiation64-218
Rapid shutdown initiatorAt the service equipment or meter location and, where practicable, at a permanent roof access or within sight of and 9 m from the array64-218
DisconnectsOpen all ungrounded conductors simultaneously, at rated load, lockable open; a combiner's disconnect integral or within 2 m and interlocked with its door64-060, 64-222
Warning signsCapital letters at least 9.5 mm high, white on red; a directory of all power sources at each service equipment location64-074, 64-076
Protection and Equipment Selection Map A PV design review should track what each box is responsible for - not just connect symbols together. PV Array Voc / Isc / temp roof routing Combiner fusing / monitoring parallel strings DC Isolation DC-rated switching labels / lockout Inverter MPPT / approval anti-islanding AC Interface disconnect / meter service capacity surge, bonding, routing string fusing lockable isolation certified inverter utility review
Protection responsibilities across a PV installation. This type of map helps keep OCP, disconnect ratings, markings, bonding, utility requirements, and equipment instructions aligned.

Where does the system connect to the building?

The output of an interactive inverter connects on the supply side of the service disconnecting means, unless the load-side provisions of Rule 64-112 are met. A load-side connection lets the combined ratings of the supply and the PV breakers exceed the busbar or conductor rating by up to 120 % (125 % in dwelling units), with conditions on where the PV breaker sits and how it is marked. On an existing switchboard that check often decides the connection point: a main switchboard with no busbar margin pushes the connection to the supply side or to a downstream board. Only inverters and ac modules marked as interactive are permitted in interactive systems (Rule 64-106).

PV Connection Point Options The best point of connection depends on PV size, load profile, feeder capacity, utility rules, and maintenance strategy. 1. Main LV switchboard PV 2. Distribution switchboard PV 3. Supply-side / upstream PV
Connection at the main switchboard, a downstream distribution switchboard, or upstream of the main switchboard can all be valid concepts. In Ontario, the final choice must be checked against OESC/CEC, utility interconnection, service ratings, and maintenance requirements.

What does the utility need?

The distributor approves the connection, and the size of the system sets the process. Toronto Hydro handles distributed energy resources of 12 kW or less with a micro-embedded generation application; larger projects need a Connection Impact Assessment (CIA) application. Hydro One uses the same 12 kW line between its net metering forms. ESA's role sits between design and connection: the Section 84 protection must be acceptable to the supply authority before ESA issues its connection authorization (Bulletin 84-1-19).

Net metering itself, the billing arrangement that credits exported energy, is covered in our solar PV net metering guide. In short, Ontario's net metering regulation applies to generation used primarily for the customer's own use and made solely from a renewable source, and credits not used within 12 months expire.

Who reviews the roof?

The roof is a structural question, answered by a structural engineer: the added dead load, wind uplift on the racking, snow drifting around the array, and the condition of the existing structure. The electrical design depends on its answer, because the accepted roof areas set the array size, but the two are separate scopes and separate sealed documents. Ask for the structural review before the array layout is fixed.

What is specific to Ontario?

  • The 29th edition rules. Rapid shutdown, dc arc-fault protection and the load-side 120 % rule are all in the current Ontario code; designs carried over from older projects need rechecking.
  • 12 kW, not 10 kW. Toronto Hydro and Hydro One now use 12 kW as the line for their simpler connection process.
  • Storage and EV charging. Batteries are also Section 64 equipment; see our battery storage electrical design guide. Our solar and distributed energy service covers the full electrical design.

Frequently Asked Questions

Does a commercial rooftop PV system need rapid shutdown in Ontario?

Yes, where the PV conductors on or in the building run more than 1 m from the array. Rule 64-218 requires those conductors to drop to not more than 30 V within 30 seconds of initiation.

How is the maximum PV string voltage calculated?

Under Rule 64-202, as the rated open-circuit voltage multiplied by 125 %, or from the lowest expected ambient temperature and the module manufacturer's temperature coefficient. That voltage sets the rating of all dc equipment.

Can the PV system connect to an existing switchboard?

On the load side, where Rule 64-112 allows: the combined breaker ratings may exceed the busbar rating by up to 120 %, with conditions on placement and marking. Otherwise the connection is on the supply side of the service disconnect.

When does the utility need a Connection Impact Assessment?

For Toronto Hydro, for distributed energy resources larger than 12 kW; projects of 12 kW or less use the micro-embedded generation application. Check the local distributor's current process.

Sources

  1. Ontario Electrical Safety Code, 29th edition, Section 64 (Rules 64-000 to 64-222).
  2. Electrical Safety Authority, Bulletin 84-1-19 (May 2025).
  3. Toronto Hydro, Distributed Energy Resource Application and Connection Guidelines; Hydro One, Net metering.
  4. O. Reg. 541/05, Net Metering, sections 7 and 8.

Related service

Electrical engineering

ETEM prepares the electrical design for rooftop PV: strings, protection, the point of connection and the documents ESA and the utility need. Describe the building.

Electrical engineering